The rebuild work by Randall Construction started in Decemeber 2025 and is progressing well with estimated completion and just over a year.

Status as at May 1

Progress Report May 1

The steel structure above the hall and kitchen area is now being erected as shown in the image.   Work was slowed down by high winds earlier in the week but as you can see it is well advance.   One can start to see the framework creating the shape that we saw much earier in the architects model.

 

Progress Report 2 Jan 27

In spite of challenging weather conditions during January, steady progress has been made with the church rebuilding. The “tolling” bell has been removed and returned to the foundry where it will be melted down and recast. It will eventually be hung at the east end of the church, replacing the bell that was badly damaged in the fire. The bell tower has now been taken down in readiness for the construction of the new entrance to the church. Demolition work continues in preparation for the new entrance and layout to the hall. The whole building is now protected with 3 metre high corrugated sheeting to make the building as safe as possible while the work continues.